Cabling Retraction, New Cable Tray Installation & Cable Reinstallation

BMA Hay Point FootBridge 3

Our team adapted to a schedule change to bring shipping and production systems back online 24 hrs early at the Hay Point Coal Terminal footbridge. This involved the removal of existing lighting and cabling, and the installation of new lighting and cable trays, including testing and commissioning under tight deadlines.

  • Supervision of rotating crews for 24 hour coverage
  • Disconnect and pull back on all electrical cabling
  • Remove of all lighting and cable trays from footbridge
  • Pre-fit lighting and cable trays to new footbridge
  • Install new cable trays at MC3
  • Fabricate cable tray mounts and re-install all cabling
  • Test and Commission all cables and MC3 – MC5 winches