ROM 1 Substation 6 Replacement

BMA Goonyella Riverside Mine

Engaged as principal contractor to complete the upgrade of the substation and manage the entire installation.

The work included:

  • Project management, site supervision and administration
  • Civil works
  • Installation of new switchroom, 11kV high voltage transformer,
    new main feeder cables, new drive motors, cable tray, plus tie in of
    new cabling to existing equipment
  • Testing and commissioning of installation
  • Compilation of MDR for client